List of steps
(Total number of steps: 45)
Meet Department of Planning and Investment (DPI) and define location
Obtain certified copies of foreign documents for consular legalization  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Declare investment project information online
Obtain Investment Registration Certificate (IRC)  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Obtain authenticated copies of IRC  (2)
Obtain seal and seal seal specimen notice  (2)
17
Make seal
Open bank account  (1)
Obtain approval of environmental impact assessment (EIA) report  (5)
Obtain agreement on land use demand  (3)
Obtain document of evaluation on demand on land use  (2)
Obtain decision on changing purpose of land use  (2)
Sign land lease contract  (2)
Attend on-site title plan verification  (1)
Obtain land use right certificate  (1)
Obtain authenticated copies of land use right certificate  (2)
Obtain planning license/ agreement on architectural planning  (3)
Make construction investment project  (1)
Obtain approval of fire prevention and fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
41
Make construction investment project
(last modified: 10/12/2016)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

Free of charge
25 mn  -  40 mn
15 days  -  30 days

Contact details

Entity in charge

ANY CONSTRUCTION AND DESIGN CONSULTANT


List of some construction consultant and design of Phu Yen List of some construction consultant and design of Phu Yen

Expected results

Conceptual plan 01 - Conceptual plan
Technical specifications of conceptual plan 01 - Technical specifications of conceptual plan
Construction designing competency report Construction designing competency report
Acceptance minutes of meeting on conceptual plan of investor 01 - Acceptance minutes of meeting on conceptual plan of investor
Report on evaluation results Report on evaluation results
1/50 - 1/200 scale fire prevention and fighting plans 01 - 1/50 - 1/200 scale fire prevention and fighting plans
Technical designs (printed on A1 or A2 sized paper) 01 - Technical designs (printed on A1 or A2 sized paper)
Detailed construction plans (printed on A1 or A2 sized paper) 01 - Detailed construction plans (printed on A1 or A2 sized paper)
Consultant unit/authority in charge's report on his/her evaluation on construction plans Consultant unit/authority in charge's report on his/her evaluation on construction plans
Investor's report on his/her evaluation and approval of the detailed constructions plans Investor's report on his/her evaluation and approval of the detailed constructions plans
Documents and drawings indicate clearly terrain of the location 01 - Documents and drawings indicate clearly terrain of the location
Specifications of detailed construction plan 01 - Specifications of detailed construction plan
Specifications of technical designs 01 - Specifications of technical designs
Documents and drawings of detailed planning 1/500 x2 01 - Documents and drawings of detailed planning 1/500
Drawing of total plane of the project or of each phase of the project 1/100-1/500 x2 01 - Drawing of total plane of the project or of each phase of the project 1/100-1/500
Drawing of plane of each work on land plot 1/50-1/200 x2 01 - Drawing of plane of each work on land plot 1/50-1/200
Drawing of the main vertical section and cross section of each work 1/50-1/200 x2 01 - Drawing of the main vertical section and cross section of each work 1/50-1/200
Drawing of substructure plane of each work 1/100 - 1/200 x2 01 - Drawing of substructure plane of each work 1/100 - 1/200
Opinion on conceptual plan of the authority in charge on specialized construction  Opinion on conceptual plan of the authority in charge on specialized construction
Approval of construction methods ensuring safety of investment works and nearly works of investor Approval of construction methods ensuring safety of investment works and nearly works of investor
The declaration of qualification , experience of design organizations The declaration of qualification , experience of design organizations
Estimates of total investment amount of planning design x2 Estimates of total investment amount of planning design
Estimates of the total investment amount of project, works x2 Estimates of the total investment amount of project, works

Requirements

1. 01 - Libre deuda de patente
Authenticated copy of land use right certificate
2. Planning licence/ Agreement on architectural planning
Planning licence/ Agreement on architectural planning (original)

Costs

Payment methods: cash, bank transfer
The fee depends on agreement between investors and consultant company

Time frame

Waiting time in queue: Min. 5mn - Max. 10mn
Attention at counter: Min. 20mn - Max. 30mn
Waiting time until next step: Min. 15 days - Max. 30 days

Legal justification

1. Law No 16/2003/QH11 of National Assembly dated November 26, 2003 on construction
Law No 16/2003/QH11 of National Assembly dated November 26, 2003 on construction
articles 46, 48, 49, 50.2, 53, 54.2.b, 56, 57
2.  Law No 38/2009/QH12 of National Assembly dated June 19, 2009 on amending law on construction
Law No 38/2009/QH12 of National Assembly dated June 19, 2009 on amending law on construction
Article 1.1
3. Decree 12/2009/NĐ-CP of Goverment dated February 10, 2009 on management of construction projects
Decree 12/2009/NĐ-CP of Goverment dated February 10, 2009 on management of construction projects
articles 8, 11.3, 13.1.b, 16.1.a, 16.2.b
4. Decree 15/2013/NĐ-CP of the Goverment dated February 06, 2013 on management of construction quality
Decree 15/2013/NĐ-CP of the Goverment dated February 06, 2013 on management of construction quality
Article 20