Meet Department of Planning and Investment (DPI) and define location
Obtain certified copies of foreign documents for consular legalization  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Declare investment project information online
Obtain Investment Registration Certificate (IRC)  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Obtain authenticated copies of IRC  (2)
Obtain seal and seal seal specimen notice  (2)
17
Make seal
Open bank account  (1)
Obtain approval of environmental impact assessment (EIA) report  (5)
Obtain agreement on land use demand  (3)
Obtain document of evaluation on demand on land use  (2)
Obtain decision on changing purpose of land use  (2)
Sign land lease contract  (2)
Attend on-site title plan verification  (1)
Obtain land use right certificate  (1)
Obtain authenticated copies of land use right certificate  (2)
Obtain planning license/ agreement on architectural planning  (3)
Make construction investment project  (1)
Obtain approval of fire prevention and fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
21
Submit application for approval of EIA report
(last modified: 10/12/2016)

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  20 mn
10 days  -  15 days

Contact details

Entity in charge

DEPARTMENT OF NATURAL RESSOURCES AND ENVIRONMENT OF PHU YEN

62 A, Le Duan Street, Ward 7 , Tuy Hoa, Phu Yen
Tel: +84 57 384 3900

Unit in charge

ONE - SHOP - STOP UNIT (PNREA)

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

MS. DOAN THI QUE NHU

Staff
Tel: +84 975 815 220, +84 57 384 1855
Email: doanquenhupy@gmail.com

Expected results

Receipt of application for approval of EIA report Receipt of application for approval of EIA report

Requirements

1. Request letter for approval of EIA report
Request letter for approval of EIA report (original)
2. Environmental impact assessment report
Environmental impact assessment report (original + 9 simple copies)
3. 01 - Libre deuda de patente
Certified translation of report on Investment project (original)

Time frame

Within 5 days after submitting the application file, investor may receive a request for additional information of the content of documents. The request could be sent by post or by fax by unit in charge of the Department of Natural Resources and Environment. After correcting or adding information as requested, investor has to return to One-stop-shop unit and submit completed application file. The waiting time to obtain approval on Environmental impact assessment report is 45 days after submitting a compete and valid application file.
Waiting time in queue: Max. 5mn
Attention at counter: Min. 10mn - Max. 15mn
Waiting time until next step: Min. 10 days - Max. 15 days

Legal justification

1. Law No 52/2005/QH11 of National Assembly dated November 29, 2011 on environmental protection
Law No 52/2005/QH11 of National Assembly dated November 29, 2011 on environmental protection
Article 21
2. Decree 29/2011/NĐ-CP of Goverment  dated April 18, 2011 on strategic environment assessments, environment impact assessments and environment protection plans
Decree 29/2011/NĐ-CP of Goverment dated April 18, 2011 on strategic environment assessments, environment impact assessments and environment protection plans
Article 13
3. Circular 26/2011/TT-BTNMT of Ministry of Natural resources and environment dated July 18, 2011 on specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environment protection plans
Circular 26/2011/TT-BTNMT of Ministry of Natural resources and environment dated July 18, 2011 on specifying some articles of Decree 29/2011/ND-CP dated 18/04/2011 by the Government re strategic environment assessments, environment impact assessments, environment protection plans
articles 10, 13, 14, 15

Who certified this information ?

Ms. Lê Đào AN XUÂN, Deputy Director, 30/01/2015

Recourse: DEPARTMENT OF NATURAL RESSOURCES AND ENVIRONMENT OF PHU YEN

Entity in charge

DEPARTMENT OF NATURAL RESSOURCES AND ENVIRONMENT OF PHU YEN

62 A, Le Duan Street, Ward 7 , Tuy Hoa, Phu Yen
Tel: +84 57 384 3900

Unit in charge

ONE - SHOP - STOP UNIT (PNREA)

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00

Person in charge

MR. NGUYỄN THANH PHONG

Deputy Head of Office/ Head of One-shop-stop unit