List of steps
(Total number of steps: 3)
Declare investment project information online
Obtain amended investment registration certificate (IRC)  (3)

Preview & Print

Properties
 
Summary of the procedure
 

Where to go? (1)

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
DEPARTMENT OF PLANNING AND INVESTMENT OF PHU YEN (x 3)
1 2 3
DEPARTMENT OF PLANNING AND INVESTMENT OF PHU YEN

What you will get (1)

The objective of the procedure is to obtain those documents.
Amended Investment registration certificate
3
Amended Investment registration certificate

Required documents 

The documents with green band will be provided to you during the procedure.

Investment registration certificate amendment application form (apdx I.7)
1
Investment registration certificate amendment application form (apdx I.7)
Documents related to the amendment of name, address of the investor or name of investment project
1
Investment registration certificate amendment application form (apdx I.6 or I.7)
1
Investment registration certificate amendment application form (apdx I.6 or I.7)
Report on investment project implementation situation to the time of amendment (apdx I.8)
1
Report on investment project implementation situation to the time of amendment (apdx I.8)
Investor's decision on amendment of investment project
1
Investment project proposal (apdx I.2)
1
Investment project proposal (apdx I.2)
Proposal of land use demand
1
Technical using explanation
1
Certified translation of legalized copy of 2 latest years audited financial report
1
Certified translation of legalized copy of 2 latest years audited financial report
Authenticated copy of passport or Vietnamese ID card of investor
1
Authenticated copy of passport or Vietnamese ID card of investor
Receipt of application of amendment IRC
3
Receipt of application of amendment IRC
Passport or Vietnamese ID card of the collecting people
3
Passport or Vietnamese ID card of the collecting people
Power of attorney from the investor to the authorized person/authority
3
Power of attorney from the investor to the authorized person/authority
Non resident
Authenticated copy of current IRC
1
Authenticated copy of current IRC

How much?

Free of charge

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  Min. Max.
Total time (sum): 1 d 3 d
of which:
Waiting time in queue (sum): 10mn 20mn
Attention at counter: 20mn 45mn
Waiting time until next step (sum): 0 d 3 d

Legal justification?

The regulations which justify the procedure and its content
Circular No. 16/2015/TT-BKHDT of the Ministry of Planning and Investment dated November 18, 2015 issuing standard forms for conducting investment procedures and report on investment in Vietnam Circular No. 16/2015/TT-BKHDT of the Ministry of Planning and Investment dated November 18, 2015 issuing standard forms for conducting investment procedures and report on investment in Vietnam
  articles apdx I.6, I.7
Decree No. 118/2015/ND-CP of the Government dated November 12, 2015 providing guidelines for implementation of a number of articles of Law on Investment Decree No. 118/2015/ND-CP of the Government dated November 12, 2015 providing guidelines for implementation of a number of articles of Law on Investment
  Article 23
Decree No. 118/2015/ND-CP of the Government dated November 12, 2015 providing guidelines for implementation of a number of articles of Law on Investment Decree No. 118/2015/ND-CP of the Government dated November 12, 2015 providing guidelines for implementation of a number of articles of Law on Investment
  Article 33
Law No. 67/2014/QH13 dated November 26 of the National Assembly on Investment Law No. 67/2014/QH13 dated November 26 of the National Assembly on Investment
  Article 40
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License