List of steps
(Total number of steps: 51)
Meet Department of Planning and Investment (DPI) and define location
Obtain certified copies of foreign documents for consular legalization  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Declare investment project information online
Obtain Investment Registration Certificate (IRC)  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Obtain authenticated copies of IRC  (2)
Obtain seal and seal seal specimen notice  (2)
17
Make seal
Open bank account  (1)
Obtain approval of environmental impact assessment (EIA) report  (5)
Obtain agreement on land use demand  (3)
Obtain document of evaluation on demand on land use  (2)
Obtain decision on changing purpose of land use  (2)
Sign land lease contract  (2)
Attend on-site title plan verification  (1)
Obtain land use right certificate  (1)
Obtain authenticated copies of land use right certificate  (2)
Obtain planning license/ agreement on architectural planning  (3)
Obtain approval of detailed planning tasks  (3)
Obtain approval of detailed planning 1/500  (3)
Make construction investment project  (1)
Obtain approval of fire prevention and fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
44
Prepare application for approval of detailed planning 1/500
(last modified: 10/12/2016)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

Free of charge
15 mn  -  25 mn
10 days  -  15 days

Contact details

Entity in charge

ANY CONSTRUCTION AND DESIGN CONSULTANT


List of some construction consultant company in Phu Yen List of some construction consultant company in Phu Yen

Expected results

General explanation of detailed planning 1/500 x3 General explanation of detailed planning 1/500
Diagram of location, and limitation of the land area, rate of 1/2.000 or 1/5.000 x3 01 - Diagram of location, and limitation of the land area, rate of 1/2.000 or 1/5.000
Current state map of the landscape architecture and construction land assessment, rate of 1/500 x3 01 - Current state map of the landscape architecture and construction land assessment, rate of 1/500
Current state maps of technical infrastructure system, rate of 1/500 x3 01 - Current state maps of technical infrastructure system, rate of 1/500
Planning map of the total land use ground rate of 1/500 x3 01 - Planning map of the total land use ground rate of 1/500
Organization diagram of space, architecture, and landscape x3 01 - Organization diagram of space, architecture, and landscape
Maps of red line boundaries, construction boundaries, protection corridors, rate of 1/500 x3 01 - Maps of red line boundaries, construction boundaries, protection corridors, rate of 1/500
Maps of technical infrastructure system planning and environment, rate of 1/500 x3 01 - Maps of technical infrastructure system planning and environment, rate of 1/500
General map of the lines, pipelines of technology, rate of 1/500 x3 01 - General map of the lines, pipelines of technology, rate of 1/500
Map of strategic environmental assessment rate of 1/500 x3 01 - Map of strategic environmental assessment rate of 1/500
Topographical maps and cadastral maps x3 01 - Topographical maps and cadastral maps
Draft regulations of management according to the detailed planning scheme x3 Draft regulations of management according to the detailed planning scheme
Draft decision of approval of detailed planning 1/500 x3 Draft decision of approval of detailed planning 1/500
CD archiving all records of the planning scheme x3 CD archiving all records of the planning scheme

Requirements

1. Approval of detailed planning tasks
Approval of detailed planning tasks (Simple copy)

Costs

Payment methods: cash, bank transfer
The fee depends on agreement between investor and consultant company

Time frame

Waiting time in queue: Min. 5mn - Max. 10mn
Attention at counter: Min. 10mn - Max. 15mn
Waiting time until next step: Min. 10 days - Max. 15 days

Legal justification

1. Law No 30/2009/QH11 of National Assembly dated June 17, 2009 on urban planning
Law No 30/2009/QH11 of National Assembly dated June 17, 2009 on urban planning
Article 35.3
2. Decree 37/2010/NĐ-CP of Goverment dated April 07, 2010 on providing guidance for development, evaluation, approval and management of urban planning
Decree 37/2010/NĐ-CP of Goverment dated April 07, 2010 on providing guidance for development, evaluation, approval and management of urban planning
articles 32, 33
3. Circular 10/2010/TT-BXD of Ministry of Construction dated August 11, 2010 on defining records of each urban planning
Circular 10/2010/TT-BXD of Ministry of Construction dated August 11, 2010 on defining records of each urban planning
articles 4, 12
4. Decision 03/2008/QD-BXD of Ministry of Construction dated March 31, 2008 on promulgating regulations on contents of drawings and explanatory statements of construction master plans and tasks
Decision 03/2008/QD-BXD of Ministry of Construction dated March 31, 2008 on promulgating regulations on contents of drawings and explanatory statements of construction master plans and tasks
articles apdx.I, II