Requirements
The investors have to submit 01 set of documents and 02 sets of drawings:
1.
Application for construction permit (original)
2.
Authenticated copy of land use right certificate
3.
Authenticated copy of investment certificate
4.
Drawing of total plane of the project or of each phase of the project 1/100-1/500 (2 original )
5.
Drawing of plane of each work on land plot 1/50-1/200 (2 original )
attaching placement diagram of work
6.
Drawing of the main vertical section and cross section of each work 1/50-1/200 (2 original )
7.
Drawing of substructure plane of each work 1/100 - 1/200 (2 original )
and cross substructure plane section of each work with ratio 1/50, attached diagram of connection with rain water drainage systems, waste water treatment, water supplying, electricity supplying and communication with ratio 1/50-1/200
Depending on the construction site, work scale and nature of the work, reference to the provisions of the regulations, construction norms, and regulations, professional standards and provisions of related national law, the application file must include, in addition to the above, the following documents:
1.
Appraisal of 1/50 - 1/200 scale fire prevention and fighting plans (original)
2.
Investor's report on his/her evaluation and approval of the detailed constructions plans (original)
3.
Consultant unit/authority in charge's report on his/her evaluation on construction plans (original)
attaching the bearing structure drawing signed and sealed by consultant unit.
4.
Opinion on conceptual plan of the authority in charge on specialized construction (original)
(if it’s appicable)
5.
Approval of construction methods ensuring safety of investment works and nearly works of investor (original)
6.
The declaration of qualification , experience of design organizations (original)
attaching authenticated copy of certificate of practicing in case of design responsible individuals
Time frame
The waiting time to collect construction permit is 10 working days after submitting regular application file.
Waiting time in queue:
Max. 5mn
Attention at counter:
Min. 15mn - Max. 20mn
Waiting time until next step:
Max. 10 days
Giang
edited
24/07/2014 07:22:00 AM
Finished
Legal justification
1.
Law No 16/2003/QH11 of National Assembly dated November 26, 2003 on construction
articles 62.1, 63, 65, 66.1
2.
Decree 12/2009/NĐ-CP of Goverment dated February 10, 2009 on management of construction projects
articles 19, 20, 22
3.
Decree 83/2009/NĐ-CP of Goverment dated October 15, 2009 on amending some articles of Decree 12/2009/ND-CP dated 12/02/2009 re construction project management
articles 5, 6
4.
Decree 64/2012/NĐ-CP of Goverment dated September 04, 2012 on re issuance of construction permits
articles 5, 8, 9, 19.a
5.
Circular 10/2012/TT-BXD of Ministry of Construction dated December 20, 2012 on guiding Decree 64/2012/NĐ-CP dated September 04, 2012 của of Goverment on issuance of construction permits
articles 2, 3, 10, 11
6.
Circular 03/2009/TT-BXD of Ministry of Construction dated 26 March 2009 on specifying Decree 12/2009/NĐ-CP on management of construction project
Article 7
7.
Decision 172/QĐ-BXD of Ministry of Construction dated February 06, 2013 on annoucing new administrative procedures
articles 1, 2
8.
Decision 821/QĐ-UBND of Phu Yen People's Committee dated June 14, 2012 on annoucing new procedures of Phu Yen construction department
Article 1
Who certified this information ?
Mr. Nguyễn VĂN ĐỒNG, Deputy Director,
30/01/2015