Meet Phu Yen Management of Economic zones Authority (PMEZA)
Obtain certified copies of foreign documents for consular legalization  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Obtain authenticated copies of IRC  (2)
Obtain seal and seal seal specimen notice  (2)
17
Make seal
Open bank account  (1)
Prepare construction investment project  (1)
Obtain approval of environmental impact assessment (EIA) report  (5)
Obtain approval of conceptual plan  (2)
Obtain approval of fire prevention and fighting  (2)
Lease land  (3)
Obtain land use right certificate  (1)
Obtain authenticated copies of land use right certificate  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
36
Submit application for construction permit
(last modified: 10/12/2016)

Timeframe ( ver detalles )

Espera hasta paso siguiente

15 mn  -  25 mn
0 days  -  10 days

Contact details

Entity in charge

DEPARTMENT OF CONSTRUCTION OF PHU YEN

02 A, Ly Tu Trong, Ward 7 , Tuy Hoa, Phu Yen
Tel: +84 57 384 2756/+84 57 384 2020
Email: sxdpy@phuyen.gov.vn
Website: http://soxaydung.phuyen.gov.vn

Unit in charge

ONE-STOP-SHOP UNIT (DC)

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00
Sat: 07:00-11:30

Person in charge

MR. NGUYEN HOANG SANH

Deputy Head of Office
Tel: +84 914 187 500, +84 57 384 2756
Email: nguyenhoangsanh@gmail.com

Expected results

Receipt of application file for construction permit 01 - Receipt of application file for construction permit

Requirements

The investors have to submit 1 set of documents and 2 sets of drawings:
1. Application for construction permit
Application for construction permit (original)
2. 01 - Libre deuda de patente
Authenticated copy of land use right certificate (an authentic copy)
3. 01 - Libre deuda de patente
Authenticated copy of IRC (an authentic copy)
4. 01 - Libre deuda de patente
Drawing of total plane of the project or of each phase of the project 1/100-1/500 (2 original )
5. 01 - Libre deuda de patente
Drawing of plane of each work on land plot 1/50-1/200 (2 original )
attaching placement diagram of work
6. 01 - Libre deuda de patente
Drawing of the main vertical section and cross section of each work 1/50-1/200 (2 original )
7. 01 - Libre deuda de patente
Drawing of substructure plane of each work 1/100 - 1/200 (2 original )
and cross substructure plane section of each work with 1/50 , attaching diagram of connection with rain water drainage systems , waste water treatment , water suppling, electricity suppling and communication with ratio 1/50-1/200
Depending on the construction site, work scale and nature of the work, reference to the provisions of the regulations, construction norms, and regulations, professional standards and provisions of related national law, the application file must include, in addition to the above, the following documents:
1. 01 - Libre deuda de patente
Appraisal of 1/50 - 1/200 scale fire protection and fighting plans (original)
2. Investor's report on his/her evaluation and approval of the detailed constructions plans
Investor's report on his/her evaluation and approval of the detailed constructions plans (original)
3. Consultant unit/authority in charge's report on his/her evaluation on construction plans
Consultant unit/authority in charge's report on his/her evaluation on construction plans (original)
attaching the bearing structure drawing signed and sealed by consultant unit.
4. Approval of conceptual plan
Approval of conceptual plan (Simple copy)
5. Approval of construction methods ensuring safety of investment works and nearly works of investor
Approval of construction methods ensuring safety of investment works and nearly works of investor (original)
6. Declaration of qualification , experience of design organizations
Declaration of qualification , experience of design organizations (original)
attaching authenticated copy of certificate of practicing in case of design responsible individuals

Time frame

The waiting time to collect construction permit is 10 working days after submitting regular application file.
Waiting time in queue: Max. 5mn
Attention at counter: Min. 15mn - Max. 20mn
Waiting time until next step: Max. 10 days

Legal justification

1. Law No 16/2003/QH11 of National Assembly dated November 26, 2003 on construction
Law No 16/2003/QH11 of National Assembly dated November 26, 2003 on construction
articles 62.1, 63, 65, 66.1
2. Decree 12/2009/NĐ-CP of Goverment dated February 10, 2009 on management of construction projects
Decree 12/2009/NĐ-CP of Goverment dated February 10, 2009 on management of construction projects
articles 19, 20, 22
3. Decree 83/2009/NĐ-CP of Goverment dated October 15, 2009 on amending some articles of Decree 12/2009/ND-CP dated 12/02/2009 re construction project management
Decree 83/2009/NĐ-CP of Goverment dated October 15, 2009 on amending some articles of Decree 12/2009/ND-CP dated 12/02/2009 re construction project management
articles 5, 6
4. Decree 64/2012/NĐ-CP of Goverment dated September 04, 2012 on re issuance of construction permits
Decree 64/2012/NĐ-CP of Goverment dated September 04, 2012 on re issuance of construction permits
articles 5, 8, 9, 19.a
5. Circular 10/2012/TT-BXD of Ministry of Construction dated December 20, 2012 on guiding Decree 64/2012/NĐ-CP dated September 04, 2012  của of Goverment on issuance of construction permits
Circular 10/2012/TT-BXD of Ministry of Construction dated December 20, 2012 on guiding Decree 64/2012/NĐ-CP dated September 04, 2012 của of Goverment on issuance of construction permits
articles 2, 3, 10, 11
6. Circular 03/2009/TT-BXD of Ministry of Construction dated 26 March 2009 on specifying Decree 12/2009/NĐ-CP on management of construction project
Circular 03/2009/TT-BXD of Ministry of Construction dated 26 March 2009 on specifying Decree 12/2009/NĐ-CP on management of construction project
Article 7
7. Decision 172/QĐ-BXD of Ministry of Construction dated February 06, 2013 on annoucing new administrative procedures
Decision 172/QĐ-BXD of Ministry of Construction dated February 06, 2013 on annoucing new administrative procedures
articles 1, 2
8. Decision 821/QĐ-UBND of Phu Yen People's Committee dated June 14, 2012 on annoucing new procedures of Phu Yen construction department
Decision 821/QĐ-UBND of Phu Yen People's Committee dated June 14, 2012 on annoucing new procedures of Phu Yen construction department
Article 1

Who certified this information ?

Mr. Nguyễn VĂN ĐỒNG, Deputy Director, 30/01/2015

Recourse: DEPARTMENT OF CONSTRUCTION OF PHU YEN

Entity in charge

DEPARTMENT OF CONSTRUCTION OF PHU YEN

02 A, Ly Tu Trong, Ward 7 , Tuy Hoa, Phu Yen
Tel: +84 57 384 2756/+84 57 384 2020
Email: sxdpy@phuyen.gov.vn
Website: http://soxaydung.phuyen.gov.vn

Unit in charge

ONE-STOP-SHOP UNIT (DC)

Mon: 07:00-11:30, 13:30-17:00
Tue: 07:00-11:30, 13:30-17:00
Wed: 07:00-11:30, 13:30-17:00
Thu: 07:00-11:30, 13:30-17:00
Fri: 07:00-11:30, 13:30-17:00
Sat: 07:00-11:30

Person in charge

MR. NGUYEN LAM HANH

Head of Office - Head of One-shop-stop unit
Tel: +84 122 254 5383, +84 57 384 2789